Wastewater Digester Lid & Miscellaneous Improvements

Wastewater Digester Lid & Miscellaneous Improvements

Project Manager

Water Resources / David Barth, P.E.

SUA Project No. 16SG01


What We're Doing

The City of Stillwater and Stillwater Utilities Authority is making improvements to multiple facilities at the Wastewater Treatment Plant. These include: two digesters, an automatic transfer switch, a gas collection system used for fueling the heat generation system, grease handling system, basin drains, fencing and roofing. 


Project Benefits

Sludge digestion produces corrosive gases that have led to the deterioration of Digester A and B lids. 


Latest Project Update

November 15, 2017: Bid Opening occurred November 18th.


Project Timeline:

May 12, 2017: The design kickoff meeting between the City and Freese and Nichols was held on May 8th. The study phase is expected to last five months.


Actions authorized by Stillwater Utilities Authority (SUA):

  • 4.17.14  | SUA-17-08 |  Authorization of Professional Services Agreement