Western Road & 32nd Avenue Water Line

Western Road from 44th Ave to Sangre Road & 32nd Avenue Water Line

Project Manager

Water Resources / Eric Fladie

SUA Project No. 15WC04, Water 2040


What We're Doing

The two miles of water line will improve service and reliability to the Deer Crossing and Woodland Trails developments and other neighborhoods along the alignment.


Project Benefits

This project is part of the Water 2040 Program. Click here for more information.


Latest Project Update

October 13, 2017: Contract awarded to McKee Utility Contractors, Inc.


Project Timeline:

July 7, 2017: Bid opening scheduled for Wednesday, Aug. 9 at 3 p.m. 

August 10, 2017: Bid opening occurred at 3 p.m. Wednesday, August 9, 2017. 


Actions authorized by Stillwater Utilities Authority (SUA):

  • 8.15.16  l SUA-16-44   l  Real Estate Aquisition


Image