Project Manager: David Barth, P.E. | City Engineering
SUA Project No. 15WC04, Water 2040
Visit the GIS Infrastructure Map to see where city infrastructure projects are happening.
The two miles of water line will improve service and reliability to the Deer Crossing and Woodland Trails developments and other neighborhoods along the alignment.
This project is part of the Water 2040 Program. Click here for more information.
July 7, 2017: Bid opening scheduled for Wednesday, Aug. 9 at 3 p.m.
August 10, 2017: Bid opening occurred at 3 p.m. Wednesday, August 9, 2017.
October 13, 2017: Contract awarded to McKee Utility Contractors, Inc.
November 15, 2017: Pre-construction meeting held on October 17th. Notice to Proceed was issued on October 30th.
February 27, 2018: Work notifications have been mailed to residents. Contractor is currently mobilizing on-site and establishing erosion control.
April 5, 2018: Installation of the water line is progressing.
July 13, 2018: Installation of the water line along Western and 32nd is complete. Contractor is currently disinfecting the new line and will tie-into the existing water line end of July.
October 11, 2018: Water line work is progressing. The Contractor is scheduled to be completed by early November 2018.
March 29, 2019: Project is substantially complete. The Contractor is currently completing punchlist items.
![]() |