Water Resources / David Barth, P.E.
SUA Project No. 10WT26
The City of Stillwater and Stillwater Utilities Authority is repairing or replacing approximately 50 manhole frames and lids in high traffic areas.
The repairs are being made to improve the driving surface of the roadways in areas along State Highway 51 (6th Avenue), U.S. Route 177 (Perkins Road) and other locations in central Stillwater.
March 15, 2017: Construction is currently underway.
July 26, 2016: A consultant was hired and the design plans are complete. The next step in the process is advertising the contract package for bids.
December 14, 2016: North Central Construction Co. is under contract for this work. A preconstruction meeting is scheduled for the beginning of January, and construction is anticipated to start shortly after.
February 27, 2017: Construction began on February 21st and will last approximately six months. Rehabilitation work at each manhole is likely to last seven to 10 days and will involve street and lane closures at the work area.
June 26, 2017: The project will be completed by mid-July; only three manholes left to complete.
September 5, 2017: Manhole rehabilitation is complete. Staff is inspecting work and Contractor is working through punch list items.
5.19.14 | SUA-14-27 | Recommendation for rejection of the bid
6.6.16 | SUA-16-27 | Amendment to Professional Services Agreement for Phase 1
![]() |
(405) 372-0025 |
![]() |
723 S. Lewis St. Stillwater, OK 74074 |
|
New City Hall Hours: Mon-Thu: 7:30 am-5:30 pm Friday: 7:30-11:30 am |