Water Utilities Engineering / Peter Armans, P.E.
SUA Project No. 12WG17
We are connecting a dead end water line on Country Club Road to the water line at the intersection north on 37th Avenue. Phase 1 of the project was completed in the fall of 2016 and consisted of 750 feet of new water line. Phase 2 will consist of 640 feet of new water line.
This project eliminates two dead end lines in the southwest part of Stillwater. This increase in water circulation will improve water quality and increase reliability for the area.
April 26, 2016: Design for Phase 1 is complete.
July 26, 2016: The notice to proceed for the contractor, Patriot Construction Services, was issued for an Aug. 1, 2016 construction start date.
September 9, 2016: Contractor has completed Phase 1.
September 21, 2017: Phase 2 is currently in design.
May 7, 2018: The design phase is currently complete and entering the bidding phase.
July 13, 2018: Project was advertised on July 1st and Pre-Bid Meeting is scheduled for July 13, 2018.
September 10, 2018: WEB Construction Inc. has been awarded the contract to complete Phase 2. Construction is expected to begin in October.
November 20, 2018: Construction is complete. The 1 year warranty phase is currently underway.