Block 34 Overhead Distribution Line Removal

Block 34 Overhead Distribution Line Removal

Project Manager: Clint Oliver, Distribution Superintendent


What We’re Doing

The Block 34 Trust Authority has requested that the overhead electric service lines be removed from the block in preparations for future site build-out.

Phase I - Block 34 – Power Removal

  • Installation of 430 feet of new three-phase primary underground distribution system along north side of 8th Avenue.

  • Remove existing overhead conductor in the alley between Duncan and Husband Streets.

  • Relocate and install secondary service line for food trucks along Duncan Street from 8th to 9th Avenue.

Phase II - Duncan Street Undergrounding of Electric Utilities

  • Installation of secondary system along the east side of Duncan Street for placement of decorative pedestals providing provisions for food truck connections.


Anticipated Milestones

  • Anticipated Date (Design):  March 2018

  • Anticipated Date (Construction): April 2019

  • Anticipated Date (Completion): July 2019


Project Benefits

Removal of the overhead electric distribution on this block will allow for future site development. 


Budget & Funding

This project will be funded with the Rate Stabilization Fund. 

  • Year Funded:  FY2019

  • Funding SourceRate Stabilization Fund

  • Project Budget: $90,000.00

  • Expenditure to date: $63,258.36


Project Management

Current Status of Project


Updates

  • 03.12.2019: Staff began compiling the materials necessary for the project.  Work on the block is scheduled to begin on April 8, 2019, to accommodate an event on the block scheduled for April 6, 2019.  Staff is evaluating beginning work on portions of the project that are not on the block prior to April 8.

  • 07.08.2019: This week crews are installing the new secondary pedestals. Once we get the new pedestals in place we can begin removing the overhead primary and secondary lines on Block 34. Weather permitting I anticipate that we will have all the overhead lines removed from Block 34 by the end of next week.

  • 09.16.2019: The remaining primary and secondary poles have been removed from Block 34. A little work remains on the west portion of Duncan Street in the area. The project is nearing completion.

  • 10.11.2019: Project Completed


Actions Authorized by Stillwater Utilities Authority (SUA)

  • 03.11.2019 | SUA-19-06 | Block 34 - Overhead Electric Service Removal Project Approval