Strickland Park Skate Park

Strickland Park Skate Park

300 S. Main

Project Manager

Events & Recreation / Jim Scott


What We're Doing

Installing new skate park at Strickland Park.


How We're Paying For It

This Community Development Block Grant project was financed in whole or in part by funds from the U.S. Department of Housing and Urban Development as administered by the Oklahoma Department of Commerce.

Stillwater City Council selected the skate park renovations as the recipient of the 2017 Community Development Block Grant at its regular meeting on May 1, 2017.

The projected cost of the project is $242,254. The Community Development Block Grant allocation is for $121,127.

The CDBG grant has a required one-to-one match for funding. Stillwater City Council approves the project(s) and funding and the City of Stillwater administers the project(s). 


Timeline


Updates

May 9, 2018: Notice to proceed given to contractor, Spohn Ranch.

July 20, 2018Construction scheduled to begin week of July 30, 2018.

Sept. 25, 2018: Earthwork is proceeding along with installation of steel and forms in preparation of installation of concrete.