Monty Karns, City Engineer
The Stillwater Regional Airport is working to replace the current apron with a new one that expands aircraft parking and operations near the terminal. This will be completed in phases.
Anticipated Date (Design): March 2021
Anticipated Date (Construction): August 2021
Anticipated Date (Completion): July 2022
This expansion allows for safer commercial operations, larger aircraft parking areas.
This project will be funded with 90% FAA AIP Grant funds and 10% with local funds.
Year Funded: FY2021
Funding Source: 90% Federal Grant/10% City of Stillwater
Project Budget: $5,400,000
Expenditure to date: $287,631.00
None at this time
08.03.2020: City Council Resolution CC-2020-14
08.24.2020: City Council General Order Item CC-20-148
Phase 3 includes the center apron.
Content last reviewed 10.26.2020
![]() |