Apron Reconstruction: Phase 2- South

Apron Reconstruction: Phase 2-South


Project Manager

Monty Karns, City Engineer


What We're Doing

The Stillwater Regional Airport is working to replace the current asphalt apron with a full-strength concrete.  This is the first of an anticipated four phases and will expand parking and commercial airline operation space near the terminal.  


Anticipated Milestones

  • Anticipated Date (Design): March 2020

  • Anticipated Date (Construction): July 2020

  • Anticipated Date (Completion): December 2020


Benefits of the Project

This expansion allows for safer commercial operations through expanded parking capacity by providing full-strength pavement capable of supporting larger aircraft.  


Budget & Funding

This project will be funded with 100% FAA AIP Grant funds. 

  • Year Funded: FY2021

  • Funding Source: 100% Federal Grant

  • Project Budget: Estimated at $6,392,495

  • Expenditure to date: $5,973,105


Project Management


Updates

  • 03.29.2020: Out to Bid

  • 04.22.2020: Bid Opening

  • 06.01.2020: Contract Award to Duit Construction

  • 06.03.2020: Final acceptance of FAA Grant for $6,039,239

  • 03.11.2021: Project Completed, Close Out Process Begins


Actions Authorized City Council

  • 11.18.2019: City Council Resolution CC-2019-25
  • 06.01.2020: City Council Bid Award CC-20-93
  • 06.15.2020: City Council Budget Amendment for Grant Receipt CC-20-101
  • 08.24.2020: City Council Budget Amendment for 100% Project Funding CC-20-148

Phase 2 is the far southern portion of the project.


Content last reviewed 08.16.2022