Monty Karns, City Engineer
The Stillwater Regional Airport is working to replace the current asphalt apron with a full-strength concrete. This is the first of an anticipated four phases and will expand parking and commercial airline operation space near the terminal.
Anticipated Date (Design): March 2020
Anticipated Date (Construction): July 2020
Anticipated Date (Completion): December 2020
This expansion allows for safer commercial operations through expanded parking capacity by providing full-strength pavement capable of supporting larger aircraft.
This project will be funded with 100% FAA AIP Grant funds.
Year Funded: FY2021
Funding Source: 100% Federal Grant
Project Budget: Estimated at $6,392,495
Expenditure to date: $5,973,105
03.29.2020: Out to Bid
04.22.2020: Bid Opening
06.01.2020: Contract Award to Duit Construction
06.03.2020: Final acceptance of FAA Grant for $6,039,239
03.11.2021: Project Completed, Close Out Process Begins
Phase 2 is the far southern portion of the project.
Content last reviewed 08.16.2022
![]() |